Which statement is least accurate about the definition of "Done"?

Prepare for the Professional Scrum Master (PSM) Certification Exam with focused study guides and challenging quizzes. Enhance your understanding with detailed explanations and tailored feedback to excel in your Scrum Master journey!

The notion of "Done" in Scrum refers to the criteria that must be met for a Product Increment to be considered complete. This definition is typically established collaboratively by the Scrum Team, which includes the Development Team and the Product Owner, rather than being solely created by the Product Owner.

The reason the statement regarding the Product Owner creating the definition of "Done" is the least accurate is that while the Product Owner plays a critical role in defining the priorities and requirements of the Product Increment, the actual criteria for "Done" should reflect the shared understanding of the entire Scrum Team, including the Development Team who understands the technical and quality aspects necessary for a product to be complete.

On the other hand, the criteria for "Done" may indeed evolve during the project as understanding and processes improve, can vary across different projects due to specific needs and context, and can also be informed by the development organization’s standards and practices. Thus, these aspects contribute to a more collaborative, adaptive, and teamwork-oriented view of what it means to achieve "Done."

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy