Which Scrum artifacts are considered ordered?

Prepare for the Professional Scrum Master (PSM) Certification Exam with focused study guides and challenging quizzes. Enhance your understanding with detailed explanations and tailored feedback to excel in your Scrum Master journey!

The correct choice identifies the Product Backlog and Sprint Backlog as the ordered Scrum artifacts. In Scrum, the concept of ordering is vital to effectively manage and prioritize work.

The Product Backlog is a refined, ordered list of everything that is needed in the product, with the items typically prioritized based on value, risk, and necessity. This ordering ensures that the most valuable features are addressed first, allowing the Scrum Team to deliver maximum value in each Sprint.

The Sprint Backlog, on the other hand, is a selection of items from the Product Backlog that the Scrum Team commits to completing in the upcoming Sprint. It is also ordered according to their priority, helping the team to focus on the most critical tasks first. This ensures that the team is aligned on what is important to achieve within the Sprint timeframe.

The other choices consist of artifacts that do not align with the Scrum framework's definition of ordered artifacts. The Development Plan and Release Plan are not official Scrum artifacts, while the Burn Down Chart, although useful for tracking progress, does not possess any prioritization or ordering mechanism like the Product and Sprint Backlogs. Understanding the importance of maintaining order among these primary artifacts is crucial for a successful Scrum implementation.