What should the Development Team and Product Owner focus on if the Sprint Backlog is incomplete?

Prepare for the Professional Scrum Master (PSM) Certification Exam with focused study guides and challenging quizzes. Enhance your understanding with detailed explanations and tailored feedback to excel in your Scrum Master journey!

When the Sprint Backlog is found to be incomplete, the Development Team and Product Owner should indeed focus on reordering tasks to ensure high value delivery. This approach aligns with the agile philosophy of prioritizing work that delivers the most value to the customer or end user.

In Scrum, the purpose of the Sprint is to achieve specific goals and provide deliverables that can be demonstrated at the end of the Sprint. If certain tasks within the Sprint Backlog cannot be completed, the team should assess which remaining tasks provide the highest value and can contribute meaningfully to the Sprint Goal. By reordering tasks, the team ensures that even if not all planned work is completed, they focus on delivering what is most critical and valuable, thereby maximizing the outcome of their efforts.

This focus on delivering high-value work supports the iterative nature of Scrum, enabling continuous improvement and responsiveness to changing circumstances. It encourages collaboration between the Development Team and Product Owner to make informed decisions about what to prioritize based on the current state of work and potential impact on stakeholder needs.

Other approaches, such as completing all original tasks as planned, may not be feasible or beneficial if it means sacrificing value or quality. Deferring uncompleted tasks to the next Sprint could lead to issues with backlog management and may