If a Sprint is cancelled, what typically happens to the "Done" Product Backlog items?

Prepare for the Professional Scrum Master (PSM) Certification Exam with focused study guides and challenging quizzes. Enhance your understanding with detailed explanations and tailored feedback to excel in your Scrum Master journey!

When a Sprint is cancelled, the "Done" Product Backlog items are typically accepted by the Product Owner if they are potentially releasable. This means that any work that meets the Definition of Done established by the Scrum Team can be considered complete and therefore available for release. The Product Owner has the authority to decide what to do with these items, whether to release them or prioritize them for future use.

This acceptance by the Product Owner is crucial because it allows the team to recognize the value of the work done during the Sprint, even if the overall Sprint was not successful or required to be cancelled for other reasons. It allows the Product Owner to maintain visibility and leverage the work that has already been completed.

In summary, the acceptance of "Done" Product Backlog items by the Product Owner signifies that they are validated as ready for consideration in the product increment and can play a role in future planning and releases.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy