How often does a Scrum Team hold a Sprint Review?

Prepare for the Professional Scrum Master (PSM) Certification Exam with focused study guides and challenging quizzes. Enhance your understanding with detailed explanations and tailored feedback to excel in your Scrum Master journey!

A Sprint Review is a key event in the Scrum framework that is held at the end of each Sprint. This meeting is an opportunity for the Scrum Team to demonstrate the work completed during the Sprint to stakeholders. It allows the team to gather feedback, make adjustments, and ensure alignment with stakeholder expectations. The timing of the Sprint Review is tied directly to the iterative nature of Scrum, where a Sprint is typically one to four weeks long, culminating in an opportunity to inspect and adapt after each iteration.

This regular cadence of holding a Sprint Review fosters transparency, collaborative decision-making, and facilitates continuous improvement of both the product and the team's processes. It ensures that all stakeholders are engaged throughout the development cycle, thus enhancing the overall effectiveness of the Scrum Team.

In contrast, holding a Sprint Review at the start of each project, monthly, or quarterly would not align with the iterative principles of Scrum, which prioritize regular inspection and adaptation based on the most recent work done.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy