How does the Scrum Team handle changes requested during a Sprint?

Prepare for the Professional Scrum Master (PSM) Certification Exam with focused study guides and challenging quizzes. Enhance your understanding with detailed explanations and tailored feedback to excel in your Scrum Master journey!

The Scrum Team follows a structured approach when it comes to handling changes during a Sprint. In Scrum, the primary focus during a Sprint is to deliver a potentially releasable increment of the product, and drastic changes are typically avoided to maintain focus and avoid disrupting the Sprint goal.

When changes are requested during a Sprint, the best practice is to add these changes to the Product Backlog for future consideration. This allows the Scrum Team to prioritize and assess the impact of the changes on their overall product development and to incorporate them in the next Sprint if deemed valuable. This way, the changes can be thoroughly discussed and evaluated along with other backlog items, ensuring a well-managed product development process.

This practice aligns with the underlying Scrum principles of transparency, inspection, and adaptation. By placing changes in the Product Backlog, the team ensures that all stakeholders' input can be considered without derailing the current Sprint's progress. This approach allows the team to maintain its commitment to the Sprint goal while still being responsive to new information or feedback.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy