During a Sprint, can the scope of work be modified?

Prepare for the Professional Scrum Master (PSM) Certification Exam with focused study guides and challenging quizzes. Enhance your understanding with detailed explanations and tailored feedback to excel in your Scrum Master journey!

The correct choice highlights that the scope of work during a Sprint can indeed be modified, but such modifications require the agreement of all stakeholders involved. This understanding is grounded in the principles of Scrum, which emphasize collaboration and adaptability.

In Scrum, while the Sprint Backlog is a commitment by the Development Team to deliver a certain set of work items by the end of the Sprint, it is also important to recognize that changes can occur. If new information arises or there are critical developments that necessitate adjustments, these changes can be addressed collaboratively. However, it's paramount that the Development Team communicates effectively with stakeholders to reach a consensus. This ensures that everyone involved understands the implications of changing the scope and agrees on the adjustments.

In this context, if there are modifications to be made, the stakeholders, including the Product Owner, should be involved to validate and prioritize the changes. The spirit of Scrum revolves around transparency, inspection, and adaptation, which is why mutual agreement is essential for any modifications to the Sprint's scope.

Being aware of the collaborative nature of Scrum and the importance of stakeholder agreement when making any changes is crucial for maintaining alignment and ensuring that everyone is on the same page regarding project goals during a Sprint.